Turnaround Specialist, Nutrien Canadian Facilities
• Reviewed and approved all work scope packages for 37 projects including Capital Projects, Capital Expenditure, and Maintenance • Reduced the overall turnaround Critical Path by 8 shifts equating to $39 million in cost savings and production time • Developed the Contracting Strategy including the Master Site Agreements (MSA’s)
- Rocanville, Saskatchewan
- Submitted by Tony Gale
- $90000000