BC Hydro Site C Clean Energy Hydro Project

A major clean energy hydroelectric project involving significant earthworks and dam construction. • Managed quarrying of 750,000 m³ of rip rap for main dam construction with incident-free operations. • Directed drill, blast, and excavation of 500,000 m³ for the spillway, completing work ahead of schedule. • Modified rail car transportation plans to mitigate CN Rail delays and minimize project disruption. • Scheduled controlled blasting operations every three days without impacting adjacent contractors.

  • Canada
  • Submitted by Craig Squires
  • $0
Ask Yuri